Electric11 completed a solar and battery installation near Carvers Lane in Attleborough. The project combined a 13.8 kWp solar array with a 7 kW FOX hybrid inverter, approximately 23 kWh of battery storage, and a failover system.

The completed system gives the property a practical way to generate renewable electricity, store surplus power, and maintain access to selected electrical circuits during a grid outage.

Responding to the Electrical Inspection

An EICR provides a record of the condition of an existing electrical installation within the inspection’s agreed scope. In this case, the findings led to a programme of remedial work at a property in Thetford.

The schedule included the main consumer unit, water and gas bonding, lighting fittings and individual accessories. In addition, it called for an isolator in the immersion cupboard.

This combination shows why the report and repair schedule need to be considered together. Replacing one visible fitting would not cover the full recorded scope. Instead, the project brought the different tasks into one programme.

For an overview of the inspection service, visit our EICR service in Thetford page.

The Recorded Scope of Work

The job notes list the following work:

  • Installation of a new consumer unit.
  • Bonding to the water and gas supplies.
  • Replacement of the damaged kitchen fitting.
  • Installation of an immersion cupboard isolator.
  • Replacement lighting fittings specified as Class II.
  • Replacement electrical accessories in white plastic.

These tasks covered both the main electrical equipment and fittings around the home. Meanwhile, the bonding work addressed another part of the installation that is less visible in everyday use.

The photographs provide context for the lighting and accessories. However, the written schedule records the broader scope, including the consumer unit and bonding work.

Installing the New Consumer Unit

A new consumer unit formed a central part of the remedial work. Often called a fuse box, this houses the protective devices serving the property’s electrical circuits.

The consumer unit replacement sat alongside the other repairs in the schedule. It was therefore one part of the overall response to the EICR findings.

For this property, the work also included lighting fittings, accessories and supply bonding. Considering those items together gives a clearer picture of the project than describing it only as a fuse box change.

Our consumer unit replacement service in Thetford provides more information for customers considering similar work. The scope for each property depends on its installation and the findings of the assessment.

Completing Water and Gas Bonding

The job notes identify bonding to the water and gas supplies as a key part of the project. This work accompanied the consumer unit replacement and the changes to individual fittings.

Protective bonding helps reduce the risk of electric shock by limiting dangerous voltage differences between relevant conductive parts. The requirements depend on the installation, so an electrician needs to assess the services and existing arrangements.

For further background, Electrical Safety First’s earthing and bonding guidance explains the role of these protective measures.

In this Thetford project, the recorded scope included both water and gas bonding. That distinguishes the work from a project concerned only with replacing lights or switches.

Replacing Lighting Fittings

The lighting work included replacement fittings specified in the notes as Class II. The project also included white plastic electrical accessories.

The photographs show several lighting styles around the property. These include round ceiling fittings, pendant lamps and wall-mounted lights within timber-panelled rooms.

The images help show the setting for the work. They also illustrate why a lighting project may involve different fitting styles across different spaces.

Our lighting installation service covers a range of domestic lighting work. For remedial projects, the selection of fittings should follow the requirements identified for the installation.

Here, the recorded specification was Class II lighting. The product selection formed part of the response to the inspection findings, alongside the changes to the consumer unit, bonding and accessories.

Addressing the Damaged Kitchen Fitting

The repair schedule also included replacing a damaged kitchen fitting. This was a separate item from the new consumer unit.

Addressing the damaged fitting brought an individual repair into the wider programme. In addition, the specified white plastic accessories provided the recorded finish for the accessory replacements.

A visible switch or fitting is only one part of an electrical installation. Nevertheless, these smaller items matter within a remedial schedule and need to be included when agreeing the work.

Installing an Immersion Cupboard Isolator

The project included a new isolator in the immersion cupboard. This added a dedicated switching point as part of the recorded remedial work.

The cupboard photograph shows white electrical accessories and cabling beside the pipework. It gives context for this part of the property, while the job notes confirm the isolator installation.

This task extended the scope beyond the main rooms. Together with the consumer unit, bonding and fitting replacements, it formed part of the project’s response to the EICR findings.

Thetford Electrical Remedial Works: Reporting and Next Steps

The job notes state that a new satisfactory EICR is to be issued upon completion of the remedial measures. They do not confirm that the final report has already been issued.

The documented position is therefore a programme of remedial work with a satisfactory EICR as the intended reporting outcome. The final inspection and reporting records should confirm that outcome.

The project brings together several types of electrical work within one property. It includes the main board, water and gas bonding, lighting, accessories and an immersion cupboard isolator.

Discuss Remedial Work for Your Property

If an electrical inspection has identified issues, the report is a useful starting point for discussing the repairs. A clear schedule helps explain which items need attention and what the proposed work will cover.

Contact Electric11 to discuss Thetford electrical remedial works or share an existing EICR. Our team can review the findings and explain the next steps for your property.

Get a Free Quote
White electrical accessories and cabling beside pipework in the immersion cupboard
Pendant lamp and white wall light in a timber-panelled room
White pendant light and ceiling pull switch beside a window and timber cupboard
Round ceiling light in the timber-panelled hallway outside the bathroom
Round white bathroom ceiling light mounted on a timber-panelled ceiling
White light switch on a timber-panelled wall beside a doorway
Illuminated round ceiling light above the entrance door in a timber-panelled hallway
White wall light in a timber-panelled room beside a window

The Electric11 Electrical Remedial Works Process

This Thetford project brought together consumer unit replacement, water and gas bonding, lighting and accessory replacements, and an immersion cupboard isolator. The recorded aim was to address the EICR findings and support a satisfactory report following completion.

Review the EICR Findings

The inspection findings provide the starting point for the remedial schedule. For this property, the recorded scope covered the consumer unit, bonding, lighting, accessories and an immersion cupboard switching point.

Define the Required Work

The schedule brings the individual repairs and replacements together. This project included Class II lighting fittings, white plastic accessories and replacement of the damaged kitchen fitting, alongside the main board and bonding work.

Carry Out the Remedial Installation

The recorded installation work includes the new consumer unit, water and gas bonding, replacement fittings and immersion cupboard isolator. These tasks address different parts of the property’s electrical installation.

Complete Verification and Reporting

The final stage is to verify the completed work and provide the appropriate documentation. The supplied notes specify a new satisfactory EICR following completion; confirmation of its issue remains outstanding.

Frequently asked
questions

Can’t find what you’re looking for?
Get in touch with any questions.

The recorded work included a new consumer unit, bonding to the water and gas supplies, replacement lighting fittings and white plastic accessories. It also included replacing a damaged kitchen fitting and installing an immersion cupboard isolator.

An earlier EICR identified issues requiring attention. The remedial schedule brought the specified repairs and replacements into one programme of work.

Yes. The job notes list a new consumer unit as part of the installation. They do not provide its make, model or protective-device specification.

The notes specify Class II replacement lighting fittings, along with white plastic electrical accessories. The exact fitting models and quantities are not confirmed.

The supplied notes say that a new satisfactory EICR is to be issued following completion of the remedial measures. They do not confirm that it has already been issued.

Contact Electric11 and share your existing report, if available. Our team can review the findings, discuss the proposed work and provide a quote.